POST CONSTRUCTION TESTING
All Prestige Airs’ systems are tested for their fitness for purpose prior to hand over of the completed system.

Existing Passive Systems

Where subsequent construction may have compromised the installation of the gas membrane or where there exists a question mark over the systems function Prestige Air can test and validate the gas membrane and the completed system.

If the gas membrane is found to be failing then the correct level of protection can be restored by the retrospective installation of a Positive Pressurisation Unit.
New Build Systems

The Clean Air Blanket range of gas protection systems all include a manifold of sub-floor probes which allows gas and pressure levels to be recorded at the point of hand over and at any time during the life of the system to demonstrate the continuing existence of the gas barrier created by the system.
   
© Prestige Air Technology Ltd 2015
Call Us Email Us